Lakeside Church at Lake Oconee
Maverick Steel Buildings converted a conventional steel design into a pre-engineered metal building for Lakeside Church at Lake Oconee in Greensboro, Georgia. The main worship building is 100′ × 125′ × 20′, 12,500 sq ft, with a 20′ × 20′ secondary building alongside. Its columns sit hidden inside the interior walls.
Greensboro, Georgia, at Lake Oconee
– Conversion from a conventional steel design to a pre-engineered metal building
– Wood truss combined with the steel roof and accents
– Column layout hidden inside the interior walls
– Extra loads and framing for LED screen walls, worship lighting, and a stage
Buildings: Two
Main worship building: 100 ft × 125 ft, 20 ft height, 12,500 sq ft
Secondary building: 20 ft × 20 ft, 400 sq ft
Total floor area: 12,900 sq ft
System: Pre-engineered metal building, converted from a conventional steel design
Roof: Wood truss combined with steel roof and accents
Columns: Hidden inside the interior walls
Special framing: Extra loads and framing to carry LED screen walls, worship lighting, and a stage
Location: Greensboro, Georgia
General contractor: Landmark Construction
The church was shopping a conventional steel design that had come in over budget and was running behind schedule.
That is a hard place to be with a building a congregation has already been told about. The design was not the problem in itself. But with the large interior span that design was much better suited for red iron construction than conventional steel.
Their original design, engineered as a pre-engineered metal building instead. The main worship structure is 100′ wide by 125′ long at a 20′ height, 12,500 sq ft, with a 20′ × 20′ secondary building alongside it.
The roof combines a wood truss with a steel roof and steel accents. The columns are hidden inside the interior walls, which is the detail that makes the room work: cleaner construction, and more usable floor in each section rather than a column standing in it.
The building also had to hold things a worship space needs and a warehouse does not. LED screen walls, worship lighting, and a stage all attach to the structure, so extra loads and extra framing were designed in to carry them.
Combining the wood truss with the steel roof and accents was harder than expected. Two framing systems meeting in one roof is a detailing problem before it is a construction problem, and it has to be solved on paper.
The answer was the column layout. Hiding it inside the interior walls gave cleaner construction and more usable room per section, and it is why the finished room reads as a worship space rather than as a steel building with chairs in it.
A building that went up faster and cost less than the conventional steel design they had been shopping, and one that is easier to change later. Retrofits with other types of construction are simpler against a PEMB frame than against the design it replaced.

Yes, and this church is the example. They came to us with a conventional steel design that was over budget and behind schedule, and the same building was re-engineered as a PEMB. The conversion also makes later retrofits with other construction types easier against the finished frame.
Yes, when the loads go in at design. On this building the LED screen walls, worship lighting, and stage all hang off the structure, so extra framing and extra load capacity were engineered in to carry them. Tell us what is going on the walls before the steel is engineered, not after.
Yes. All of Georgia sits inside our erection radius, roughly an eight-hour drive out from the shop. Inside that radius we manufacture the building and put it up, so you get a finished building rather than a shipment. Georgia is one of our three priority markets, with South Carolina and North Carolina.
Tell us the width, the length, and what is going on the walls, and we will price it with tax and freight in the number. Bring the design you already have if you have one. Come with questions.
Drawings in weeks, not months.
Because our engineers and detailers work for us, drawings usually come back in two to four weeks and anchor bolt reactions in a day or two. Your quote arrives with a 30-page drawing set, and a CAD file you can lay over your architecturals. You see the whole building before you sign avoiding delays and rework later.
One stop, through erection.
One company manufactures your building, supplies the doors, insulation, and stamped foundation plans, and erects it, so a GC without a steel crew doesn't have to find one. When the steel goes up, the building is sealed in, and the quote includes tax and freight. We erect across the Southeast and travel farther for larger jobs.
One person who can answer.
The person who designs and prices your building stays with you until it's finished, whether it's a straightforward shop or a job with crane beams, steeples, and wide bays. If something comes up on site, during erection or after, you know who to call to get it fixed fast.
Built for the GC.
We sell to general contractors and don't compete with them. Your salesperson works as a consultant on the PEMB, helping you and the owner decide what the building needs, from panel type and insulation to door and eave heights, instead of just pricing the drawings. Because crews get paid fast, they show up when the job needs them.
100% American made steel.
Don’t want to wait?
Call now!